"There's a lot of people that use that road to cut through to other parts of the county."
Baxter city engineer Tom Bennett said that to UCNow in December 2022, while Rogers Group crews were paving Ditty Road in freezing weather. The road had been closed since June 20 that year so utilities could be extended to Portobello America. Almost four years later, Ditty Road is closed again. This time the cause is the same kind of buried infrastructure.
TDOT closed the stretch between Baxter Road and the Portobello America entrance on March 2, 2026, and expected the closure to last about six months. On a six-month timeline the road would have reopened around Labor Day. As of this week, the detour is close to eight months old.
The reason for the delay explains the whole project, because the pipes and lines under Ditty Road have set its schedule since 2022.
Why the Detour Outlasted Its Estimate
On October 18, UCNow reported that the closure had run past its original estimate because of utility relocation problems. TDOT Regional Communications Officer Rae-Anne Bradley said utilities that were expected to have been moved were still in the path of construction. Crews had to relocate them and change the order of the work.
Bradley also explained why the road is fully closed rather than open to one lane. "Essentially a decision was made that it was actually quicker and better and safer for our crews to completely close this section of Ditty Road," she told UCNow, "because there was so much that needed to be done here."
The utilities were supposed to be cleared before the road work began. In October 2025, Baxter aldermen awarded John T. Hall Construction the only bid, estimated at $1 million, to relocate utility lines on Ditty Road. UCNow's report on that vote said TDOT would not bid out the road project until those lines were moved. The work covered about 800 feet of water main and 600 feet of gravity sewer. That step came first, and utilities still turned out to be the slowest part of the 2026 schedule.
One Road, Three Rounds of Underground Work
Every long pause on Ditty Road has involved something underground.
- December 2018. The state announced that Portobello America, a ceramic tile maker, would build its first U.S. production plant and U.S. headquarters on the former Tennessee Motor Speedway site in Baxter. The announcement projected a $150 million investment and 220 jobs.
- November 2019. Mayor John Martin told UCNow that the plan called for a third lane from the interstate up Baxter Road and a new east-west road running parallel to Portobello. He said Baxter had signed a contract for TDOT assistance.
- June 2022. TDOT had started acquiring property. Martin called it a $4.2 million project, with Baxter responsible for half of the property acquisition. That was his estimate at the time, not a final contract figure.
- June 20 to December 2022. Ditty Road closed while utilities were extended to the plant. After the closure, the city council lowered the speed limit from 30 to 25 miles per hour.
- Fall 2023. The Portobello plant opened. By March 2024 it measured 986,000 square feet, and a 100,000-square-foot addition was being designed to add warehouse space.
- October 2025. The city awarded the $1 million utility relocation bid so TDOT could move forward.
- March 2, 2026. The full closure began, with a six-month estimate.
- October 18, 2026. Utility conflicts pushed the reopening back, and TDOT gave November 30 as the target for finishing the overall project.
That's about seven years from the first public description of the road plan to a projected finish. For most of that time, the work that could be seen from the road was waiting on work underground.
What Is Built, and What Is Left
Most of the new road is done. Bradley told UCNow the new alignment of Ditty Road is "essentially complete." In June, Bennett told UCNow that Rogers Group and TDOT had built the route up to the point where it ties into old Ditty Road, and that the Baxter Road widening was underway.
According to TDOT's March release, the finished road has:
- Two 12-foot travel lanes with 4-foot shoulders
- Two new box culverts along the new alignment
- An extended box culvert on Baxter Road to make room for the widening
- A left-turn lane from Baxter Road onto Ditty Road
- New pavement markings and permanent striping when construction is complete
Before the closure lifts, three things remain. Final asphalt and striping are still needed on the new alignment. The biggest remaining job is rebuilding about 800 feet of the existing Ditty Road near the Portobello entrance. Bradley said that section does not need major grading or culvert work.
The Order of the Reopening
The road won't open to everyone at once. Portobello America traffic will move onto the new alignment first, and local drivers will stay on the detour until the old section near the plant entrance is rebuilt.
So for a while, plant trucks may be using new pavement while everyone else still takes the long way. Through the whole closure, TDOT has directed Portobello traffic to SR 135, South Willow Avenue, to reach Ditty Road. Local drivers have used Baxter Road south to Academy Road, then Academy Road back to Ditty Road.
The entire project exists because of that split. It is part of TDOT's State Industrial Access program, which pays for road access to new and expanding industries. The Baxter project creates a new route for trucks traveling to and from the Portobello America plant. As far back as 2019, Mayor Martin described the industrial access road as necessary for the extra truck traffic the plant would bring.
Bradley described who the changes are meant for. "So these changes are going to make these roads safer, increase capacity and traffic flow, hopefully both for the industrial site, but also the local users that use these roads," she told UCNow.
Baxter Road Keeps Its Cones a Little Longer
When Ditty Road reopens, the work in the area won't be finished. UCNow's October report said construction will continue on Baxter Road after Ditty Road reopens. That work includes widening, a dedicated turn lane for southbound traffic coming off I-40, and box culvert installation and extensions.
No separate finish date has been announced for the Baxter Road work. If you use the interstate exit regularly, plan on construction there into the winter, even after Ditty Road opens.
This is also the third lane Martin described in 2019, running from the interstate up Baxter Road. That part of the plan was described first and will be finished last.
Treat November 30 as a Target
TDOT's announcements have described this project as weather-dependent from the beginning. The six-month estimate from March has already slipped once, and November 30 is TDOT's target for the overall project. It is not a promise about when local traffic gets back on the road. The 2022 closure ended the same way. Rogers Group was paving in cold weather, and Bennett said the road could reopen anywhere from two days to a few weeks out, depending on the weather.
For the most current status, TDOT points drivers to its SmartWay map and to the 511 travel line. When the road opens, drivers will have a wider Ditty Road with shoulders and a turn lane at Baxter Road, and Portobello's trucks will have their own route to the plant.
Road projects like this one change how a part of town works day to day, from the trip to I-40 to how traffic moves past the homes along Baxter Road. If you own property near the Ditty Road and Baxter Road corridor and want to know how the finished work might affect its value, Robbie Porter is glad to walk through it with you. Get your free home valuation, and we'll look at your property alongside what's changing around it.